WAPPENSHALL – THE RETAINING WALL IS STARTED

In miserable weather, over Friday and Saturday 20th/21st November, “Team Wappenshall” did a fantastic job to get the first 16 feet section of the East Basin’s new retaining wall built. This involved making the formwork sections from sheets of 18mm plywood and strong timber to take the weight of the concrete that was poured, by hand, into the “mould” that the formwork made around the reinforcement frame. Just another 9 sections to go now!

Image may contain: tree, bridge, plant, outdoor and nature
The formwork is finally in place ready for the first pour.
Image may contain: 2 people, people standing and outdoor
Marion and Martin check that all is ready for the concrete.
Image may contain: one or more people and outdoor
William, Steve and Marion putting the finishing touches to the wall.